Expansion of Hong Kong International Airport into a Three-Runway System |
Construction Phase Monthly EM&A Report No.47 (For November 2019) |
Contents
3RS |
Three-Runway System |
AAHK |
Airport Authority Hong Kong |
AECOM |
AECOM Asia Company Limited |
AFCD |
Agriculture, Fisheries and Conservation Department |
AIS |
Automatic Information System |
ANI |
Encounter Rate of Number of Dolphins |
APM |
Automated People Mover |
AW |
Airport West |
BHS |
Baggage Handling System |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CNP |
Construction Noise Permit |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DEZ |
Dolphin Exclusion Zone |
DO |
Dissolved Oxygen |
EAR |
Ecological Acoustic Recorder |
EIA |
Environmental Impact Assessment |
EM&A |
Environmental Monitoring & Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ET |
Environmental Team |
FCZ |
Fish Culture Zone |
HDD |
Horizontal Directional Drilling |
HKBCF |
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities |
HKIA |
Hong Kong International Airport |
HOKLAS |
Hong Kong Laboratory Accreditation Scheme |
HSF |
High Speed Ferry |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
LKC |
Lung Kwu Chau |
MMHK |
Mott MacDonald Hong Kong Limited |
MMWP |
Marine Mammal Watching Plan |
MSS |
Maritime Surveillance System |
MTRMP-CAV |
Marine Travel Routes and Management Plan for Construction and Associated Vessel |
NEL |
Northeast Lantau |
NWL |
Northwest Lantau |
PAM |
Passive Acoustic Monitoring |
SC |
Sha Chau |
SCLKCMP |
Sha Chau and Lung Kwu Chau Marine Park |
SS |
Suspended Solids |
SSSI |
Site of Special Scientific Interest |
STG |
Encounter Rate of Number of Dolphin Sightings |
SWL |
Southwest Lantau |
T2 |
Terminal 2 |
The Project |
The Expansion of Hong Kong International Airport into a Three-Runway System |
The SkyPier Plan |
Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier |
The Manual |
The Updated EM&A Manual |
TSP |
Total Suspended Particulates |
WL |
West Lantau |
WMP |
Waste Management Plan |
The “Expansion of Hong Kong
International Airport into a Three-Runway System” (the Project) serves to meet
the future air traffic demands at Hong Kong International Airport (HKIA). On 7
November 2014, the Environmental Impact Assessment (EIA) Report (Register No.:
AEIAR-185/2014) for the Project was approved and an Environmental Permit (EP)
(Permit No.: EP-489/2014) was issued for the construction and operation of the
Project.
Airport Authority Hong Kong
(AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the
role of Environmental Team (ET) for carrying out the Environmental Monitoring
& Audit (EM&A) works during the construction phase of the Project in
accordance with the Updated EM&A Manual (the Manual).
This is the 47th
Construction Phase Monthly EM&A Report for the Project which summarises the
monitoring results and audit findings of the EM&A programme during the
reporting period from 1 to 30 November 2019.
Key Activities in the Reporting
Period
The key
activities of the Project carried out in the reporting period included
reclamation works and land-side works. Reclamation works included deep cement
mixing (DCM) works, marine filling, and seawall construction. Land-side works
involved mainly airfield works, foundation and substructure work for Terminal 2
expansion, modification and tunnel work for Automated People Mover (APM) and
Baggage Handling System (BHS), and preparation work for utilities, with
activities include site establishment, site office construction, road and
drainage works, cable ducting, demolition, piling, and excavation works.
EM&A Activities Conducted in the Reporting Period
The
monthly EM&A programme was undertaken in accordance with the Manual of the
Project. Summary of the monitoring activities during this reporting period is
presented as below:
Monitoring Activities |
Number of Sessions |
1-hour Total Suspended Particulates (TSP) air quality monitoring |
36 |
Noise monitoring |
20 |
Water quality monitoring |
13 |
Vessel line-transect surveys for Chinese White Dolphin (CWD) monitoring |
2 |
Land-based theodolite tracking survey effort for CWD monitoring |
3 |
Environmental auditing works,
including weekly site inspections of construction works conducted by the ET and
bi-weekly site inspections conducted by the Independent Environmental Checker
(IEC), audit of SkyPier High Speed Ferries (HSF), audit of construction and
associated vessels, and audit of implementation of Marine Mammal Watching Plan
(MMWP) and Dolphin Exclusion Zone (DEZ) Plan, were conducted in the reporting
period. Based on information including ET’s observations, records of Maritime
Surveillance System (MSS), and contractors’ site records, it is noted that
environmental pollution control and mitigation measures were properly
implemented and construction activities of the Project in the reporting period
did not introduce adverse impacts to the sensitive receivers.
Snapshots of EM&A
Activities in the Reporting Period
|
|
|
Fill Materials Transportation Records Checking Conducted by ET |
Small Vessel Line-transect Survey of CWD Conducted by ET |
Inspection on Construction Material Sorting Facility in Area 11 |
Results of Impact
Monitoring
The monitoring works for
construction dust, construction noise, water quality, construction waste, landscape & visual, and CWD were conducted during
the reporting period in accordance with the Manual.
Monitoring results of
construction dust, construction noise, construction waste, and CWD did not
trigger the corresponding Action and Limit Levels in the reporting
period.
The water quality monitoring
results for dissolved oxygen (DO), turbidity, total alkalinity, chromium and
nickel obtained during the reporting period were within the corresponding
Action and Limit Levels stipulated in the EM&A programme. Relevant
investigation and follow-up actions will be conducted according to the EM&A
programme if the corresponding Action and Limit Levels are triggered. For
suspended solids (SS), one testing result triggered the relevant Action Level,
and the corresponding investigation was conducted accordingly. The
investigation findings concluded that the case was not related to the Project.
To conclude, the construction activities in the reporting period did not
introduce adverse impact to all water quality sensitive receivers.
Summary of Upcoming Key
Issues
Advanced Works:
Contract
P560 (R) Aviation Fuel Pipeline Diversion Works
● Stockpiling
of compressed materials
DCM Works:
Contract 3205 DCM works
●
DCM works
Reclamation Works:
Contract 3206 Main Reclamation
Works
● Land base ground improvement
works;
● Seawall construction; and
● Marine filling.
Airfield Works:
Contract 3301 North Runway Crossover Taxiway
● Cable
ducting works;
● Subgrade
compaction and paving works;
● Drainage
construction works;
● Operation
of aggregate mixing facility; and
● Precast
of duct bank and fabrication of steel works.
Contract 3302 Eastern Vehicular Tunnel Advance Works
● Cable
laying and ducting works;
● Trench
excavation works;
● Backfilling
and reinstatement works; and
● Site
establishment.
Contract 3303 Third Runway and Associated Works
● Plant
and equipment mobilisation
● Footing
and utilities work; and
● Site
establishment.
Third Runway Concourse and
Integrated Airport Centres Works:
Contract 3402 New Integrated Airport Centres Enabling Works
● Lateral
supports and excavation works;
● Drawpit
and duct laying works;
● Manhole
and pipe construction works; and
● Site
establishment.
Terminal 2 Expansion Works:
Contract 3501 Antenna Farm and Sewage Pumping Station
● Drainage
works;
● Boring
works; and
● Pipe
installation.
Contract 3502 Terminal 2 Automated People Mover (APM) Depot
Modification Works
● Site
clearance.
Contract 3503 Terminal 2 Foundation and Substructure Works
● Site establishment;
● Utilities, drainage, and road
work; and
● Piling and structure works.
Automated People Mover (APM)
Works:
Contract 3602 Existing APM System Modification Works
● Site
establishment; and
● Modification
works at APM depot.
Airport Support Infrastructure & Logistic Works:
Contract 3721 Construction Support Infrastructure Works
● Excavation
for utilities works; and
● Construction
of utilities.
Contract 3801 APM and BHS Tunnels on Existing Airport
Island
● Site
establishment;
● Cofferdam
installation for box culvert;
● Rising
main installation;
● Drilling
and grouting works;
● Piling
and foundation works
● Demolition
works; and
● Site
clearance.
The following table summarises the key findings of the
EM&A programme during the reporting period:
Yes |
No |
Details |
Analysis / Recommendation / Remedial Actions |
|
Breach of Limit Level^ |
|
√ |
No breach of Limit Level was recorded. |
Nil |
Breach of Action Level^ |
|
√ |
No breach of Action Level was recorded. |
Nil |
|
√ |
No construction activities-related complaint was received |
Nil |
|
Notification of any summons and status of prosecutions |
|
√ |
No notification of summons or prosecution was received.
|
Nil |
Change that affect the EM&A |
|
√ |
There was no change to the construction works that may affect the EM&A. |
Nil |
Note:
^ Only triggering of Action or Limit Level found related to Project works is counted as Breach of Action or Limit Level.
On 7 November 2014, the
Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) for
the “Expansion of Hong Kong International Airport into a Three-Runway System”
(the Project) was approved and an Environmental Permit (EP) (Permit No.:
EP-489/2014) was issued for the construction and operation of the Project.
Airport Authority Hong Kong
(AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the
role of Environmental Team (ET) for carrying out the Environmental Monitoring
& Audit (EM&A) works during the construction phase of the Project in
accordance with the Updated EM&A Manual (the Manual) submitted under EP
Condition 3.1[1].
AECOM Asia Company Limited (AECOM) was employed by AAHK as the Independent
Environmental Checker (IEC) for the Project.
The Project covers the expansion
of the existing airport into a three-runway system (3RS) with key project
components comprising land formation of about 650 ha and all associated
facilities and infrastructure including taxiways, aprons, aircraft stands, a
passenger concourse, an expanded Terminal 2, all related airside and landside
works and associated ancillary and supporting facilities. The submarine
aviation fuel pipelines and submarine power cables also require diversion as
part of the works.
Construction of the Project is to
proceed in the general order of diversion of the submarine aviation fuel
pipelines, diversion of the submarine power cables, land formation, and
construction of infrastructure, followed by construction of superstructures.
The updated overall
phasing programme of all construction works was presented in Appendix A of the
Construction Phase Monthly EM&A Report No. 7 and the contract information
was presented in Appendix A of the Construction Phase Monthly EM&A Report
No. 46.
This is the 47th
Construction Phase Monthly EM&A Report for the Project which summarises the
key findings of the EM&A programme during the reporting period from 1 to 30
November 2019.
The Project’s organisation
structure presented in Appendix B of the Construction Phase Monthly EM&A
Report No.1 remained unchanged during the reporting period. Contact details of
the key personnel are presented in Table 1.1.
Table 1.1: Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Project Manager’s Representative (Airport Authority Hong Kong) |
Principal Manager, Environment |
Lawrence Tsui |
2183 2734 |
Environmental Team (ET) (Mott MacDonald Hong Kong Limited) |
Environmental Team Leader |
Terence Kong |
2828 5919 |
|
Deputy Environmental Team Leader |
Heidi Yu |
2828 5704 |
|
Deputy Environmental Team Leader |
Daniel Sum |
2585 8495 |
Independent Environmental Checker (IEC) (AECOM Asia Company Limited) |
Independent Environmental Checker |
Jackel Law |
3922 9376
|
|
Deputy Independent Environmental Checker |
Roy Man |
3922 9141 |
Advanced Works:
Party |
Position |
Name |
Telephone |
Contract P560(R) Aviation Fuel Pipeline Diversion Works (Langfang Huayuan Mechanical and Electrical Engineering Co., Ltd.) |
Project Manager
|
Wei Shih
|
2117 0566
|
Environmental Officer |
Lyn Liu
|
5172 6543
|
Deep Cement Mixing (DCM) Works:
Party |
Position |
Name |
Telephone |
Contract 3205 DCM (Package 5) (Bachy Soletanche - Sambo Joint Venture) |
Deputy Project Director |
Min Park |
9683 0765 |
Environmental Officer |
William Chan |
5408 3045 |
Reclamation Works:
Party |
Position |
Name |
Telephone |
Contract 3206 Main Reclamation Works (ZHEC-CCCC-CDC Joint Venture)
|
Project Manager |
Kim Chuan Lim
|
3763 1509 |
Environmental Officer |
Kwai Fung Wong |
3763 1452 |
Airfield Works:
Party |
Position |
Name |
Telephone |
Contract 3301 North Runway Crossover Taxiway (FJT-CHEC-ZHEC Joint Venture) |
Deputy Project Director |
Kin Hang Chung |
9800 0048 |
Environmental Officer |
Joe Wong |
6182 0351 |
|
Contract 3302 Eastern Vehicular Tunnel Advance Works (China Road and Bridge Corporation) |
Project Manager
|
Wan Cheung Lee
|
6100 6075
|
Environmental Officer |
Wilmer Ng |
3919 9421 |
|
Contract 3303 Third Runway and Associated Works (SAPR Joint Venture) |
Project Manager |
Andrew Keung |
6277 6628 |
Environmental Officer |
Pan Fong |
9436 9435 |
Third Runway Concourse
and Integrated Airport Centres Works:
Party |
Position |
Name |
Telephone |
Contract 3402 New Integrated Airport Centres Enabling Works (Wing Hing Construction Co., Ltd.) |
Contract Manager |
Michael Kan |
9206 0550 |
Environmental Officer |
Lisa He |
5374 3418 |
Terminal 2 (T2)
Expansion Works:
Party |
Position |
Name |
Telephone |
Contract 3501 Antenna Farm and Sewage Pumping Station (Build King Construction Ltd.) |
Contracts Manager
|
Vincent Kwan
|
9833 1313
|
Environmental Officer |
Edward Tam |
9287 8270 |
|
Contract 3502 Terminal 2 APM Depot Modification Works (Build King Construction Ltd.) |
Project Manager |
David Ng |
9010 7871 |
Environmental Officer |
Chun Pong Chan |
9187 7118 |
|
Contract 3503 Terminal 2 Foundation and Substructure Works (Leighton – Chun Wo Joint Venture) |
Project Manager |
Eric Wu |
3973 1718 |
Environmental Officer |
Malcolm Leung |
3973 0850 |
Automated People Mover (APM) Works: |
|||
Party |
Position |
Name |
Telephone |
Contract 3602 Existing APM System Modification Works (Niigata Transys Co., Ltd.) |
Project Manager |
Kunihiro Tatecho |
9755 0351 |
Environmental Officer |
Arthur Wong |
9170 3394 |
Baggage Handling System (BHS) Works: |
||||
Party |
Position |
Name |
Telephone |
|
Contract 3603 3RS Baggage Handling System (VISH Consortium) |
Project Manager |
Andy Ng |
9102 2739 |
|
Environmental Officer |
Eric Ha |
9215 3432 |
|
Airport Support Infrastructure and Logistic Works: |
|||
Party |
Position |
Name |
Telephone |
Contract 3721 Construction Support Infrastructure Works (China State Construction Engineering (Hong Kong) Ltd.) |
Site Agent |
Thomas Lui |
9011 5340 |
Environmental Officer |
Gary Hong |
6015 0795 |
|
Contract 3801 APM and BHS Tunnels on Existing Airport Island (China State Construction Engineering (Hong Kong) Ltd.) |
Project Manager |
Tony Wong |
9642 8672 |
Environmental Officer |
Fredrick Wong |
9842 2703 |
The key activities of the Project carried out in the
reporting period included reclamation works and land-side works. Reclamation
works included deep cement mixing (DCM) works, marine filling, and seawall
construction. Land-side works involved mainly airfield works, foundation and
substructure work for Terminal 2 expansion, modification and tunnel work for
Automated People Mover (APM) and Baggage Handling System (BHS) systems, and
preparation work for utilities, with activities include site establishment,
site office construction, road and drainage works, cable ducting, demolition of
existing facilities, piling, and excavation works.
The
locations of key construction activities are presented in Figure 1.1.
The
status for all environmental aspects are presented in Table 1.2. The EM&A requirements
remained unchanged during the reporting period and details can be referred to
Table 1.2 of the Construction Phase Monthly EM&A Report No. 1.
Table 1.2:
Summary of status for all environmental aspects under the Updated EM&A
Manual
Parameters |
Status |
Air Quality |
|
Baseline Monitoring |
The baseline air quality monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
On-going |
Noise |
|
Baseline Monitoring |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
On-going |
Water Quality |
|
General Baseline Water Quality Monitoring for reclamation, water jetting and field joint works |
The baseline water quality monitoring result has been reported in Baseline Water Quality Monitoring Report and submitted to EPD under EP Condition 3.4. |
General Impact Water Quality Monitoring for reclamation, water jetting and field joint works |
On-going |
Initial Intensive Deep Cement Mixing (DCM) Water Quality Monitoring |
The Initial Intensive DCM Monitoring Report was submitted and approved by EPD in accordance with the Detailed Plan on DCM. |
Regular DCM Water Quality Monitoring |
On-going |
Waste Management |
|
Waste Monitoring |
On-going |
Land Contamination |
|
Supplementary Contamination Assessment Plan (CAP) |
The Supplementary CAP was submitted to EPD pursuant to EP Condition 2.20. |
Contamination Assessment Report (CAR) for Golf Course |
The CAR for Golf Course was submitted to EPD. |
Contamination Assessment Report (CAR) for Terminal 2 Emergency Power Supply System No.1 (Volume 1) |
The CAR for Terminal 2 Emergency Power Supply System No.1 (Volume 1) was submitted to EPD pursuant to EP Condition 1.9. |
Terrestrial Ecology |
|
Pre-construction Egretry Survey Plan |
The Egretry Survey Plan was submitted and approved by EPD under EP Condition 2.14. |
Ecological Monitoring |
The terrestrial ecological monitoring at Sheung Sha Chau was completed in January 2019. |
Marine Ecology |
|
Pre-Construction Phase Coral Dive Survey |
The Coral Translocation Plan was submitted and approved by EPD under EP Condition 2.12. |
Coral Translocation |
The coral translocation was completed. |
Post-Translocation Coral Monitoring |
The post-translocation monitoring programme according to the Coral Translocation Plan was completed in April 2018. |
Chinese White Dolphins (CWD) |
|
Vessel Survey, Land-based Theodolite Tracking and Passive Acoustic Monitoring (PAM) |
|
Baseline Monitoring |
Baseline CWD results were reported in the CWD Baseline Monitoring Report and submitted to EPD in accordance with EP Condition 3.4. |
Impact Monitoring |
On-going |
Landscape & Visual |
|
Landscape & Visual Plan |
The Landscape & Visual Plan was submitted to EPD under EP Condition 2.18 |
Baseline Monitoring |
The baseline landscape & visual monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
On-going |
Environmental Auditing |
|
Regular site inspection |
On-going |
Marine Mammal Watching Plan (MMWP) implementation measures |
On-going |
Dolphin Exclusion Zone (DEZ) Plan implementation measures |
On-going |
SkyPier High Speed Ferries (HSF) implementation measures |
On-going |
Construction and Associated Vessels Implementation measures |
On-going |
Complaint Hotline and Email channel |
On-going |
Environmental Log Book |
On-going |
Taking into account the
construction works in this reporting period, impact monitoring of air quality,
noise, water quality, waste management, landscape & visual, and CWD were
carried out in the reporting period.
The EM&A programme also
involved weekly site inspections and related auditing conducted by the ET for
checking the implementation of the required environmental mitigation measures
recommended in the approved EIA Report. To promote
the environmental awareness and enhance the environmental performance of the
contractors, environmental trainings and regular environmental management
meetings were conducted during the reporting period, which are
summarised as below:
● One skipper training session
provided by ET: 20 November 2019
● Nine environmental management
meetings for EM&A review with works contracts: 1, 11, 13, 20, 21, 25, 26
and 29 November 2019
The EM&A programme has been following the recommendations presented in the approved EIA Report and the Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix A.
Air quality monitoring of 1-hour
Total Suspended Particulates (TSP) was conducted three times every six days at
two representative monitoring stations in the vicinity of air sensitive
receivers in Tung Chung and villages in North Lantau in accordance with the
Manual. Table 2.1
describes the details of the monitoring stations. Figure 2.1 shows the locations of the
monitoring stations.
Table 2.1: Locations of Impact
Air Quality Monitoring Stations
Monitoring Station |
Location |
AR1A |
Man Tung Road Park |
AR2 |
Village House at Tin Sum |
In accordance with the Manual,
baseline air quality monitoring of 1-hour TSP levels at the two air quality
monitoring stations were established as presented in the Baseline Monitoring
Report. The Action and Limit Levels of the air quality monitoring stipulated in
the EM&A programme for triggering the relevant investigation and follow-up
procedures under the programme are provided in Table 2.2.
Table 2.2:
Action and Limit Levels of Air Quality Monitoring
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AR1A |
306 |
500 |
AR2 |
298 |
Portable direct reading dust
meter was used to carry out the air quality monitoring. Details of equipment
used in the reporting period are given in Table 2.3.
Table
2.3: Air Quality Monitoring Equipment
Brand and Model |
Last Calibration Date |
Calibration Certificate Provided in |
|
Portable direct reading dust meter (Laser dust monitor) |
SIBATA LD-3B-2 (Serial No. 296098) |
24 Oct 2019 |
Monthly EM&A Report No. 46, Appendix E |
SIBATA LD-3B-1 |
19 Sep 2019
|
Monthly EM&A Report No. 45, Appendix D |
The measurement procedures involved in the impact air
quality monitoring can be summarised as follows:
a. The portable direct reading dust meter
was mounted on a tripod at a height of 1.2m above the ground.
b. Prior to the measurement, the
equipment was set up for 1 minute span check and 6 second background check.
c. The one hour dust measurement was
started. Site conditions and dust sources at the nearby area were recorded on a
record sheet.
d. When the measurement completed, the
“Count” reading per hour was recorded for result calculation.
The
portable direct reading dust meter is calibrated every year against high volume
sampler (HVS) to check the validity and accuracy of the results measured by
direct reading method. The calibration record of the HVS provided in Appendix E
of the Construction Phase Monthly EM&A Report No. 46, and the calibration
certificates of portable direct reading dust meters
listed in Table 2.3
are valid in the reporting period.
The air quality monitoring schedule involved
in the reporting period is provided in Appendix B.
The air quality monitoring results in the reporting period
are summarised in Table
2.4. Detailed impact monitoring results are presented
in Appendix C.
Table 2.4: Summary of Air Quality
Monitoring Results
Monitoring Station |
1-hr TSP Concentration Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AR1A |
14 - 92 |
306 |
500 |
AR2 |
11 - 95 |
298 |
The monitoring results were
within the corresponding Action and Limit Levels at all monitoring stations in
the reporting period.
General meteorological conditions
throughout the impact monitoring period were recorded. Wind data including wind
speed and wind direction for each monitoring day were collected from the Chek
Lap Kok Wind Station.
No dust emission source from Project activities was observed during impact air quality monitoring. No major sources of dust was observed at the monitoring stations during the monitoring sessions. It is considered that the monitoring work in the reporting period is effective and there was no adverse impact attributable to the Project activities.
Noise monitoring in the form of
30-minute measurements of Leq, L10, and L90
levels was conducted once per week between 0700 and 1900 on normal weekdays at
four representative monitoring stations in the vicinity of noise sensitive
receivers in Tung Chung and villages in North Lantau in accordance with the
Manual. Table 3.1 describes the details of the monitoring stations. Figure 2.1 shows the locations of the
monitoring stations.
Table
3.1: Locations of Impact Noise Monitoring Stations
Monitoring Station |
Location |
Type of measurement |
NM1A |
Man Tung Road Park |
Free field |
NM2(1) |
Tung Chung West Development |
To be determined |
NM3A(2) |
Site Office |
Facade |
NM4 |
Ching Chung Hau Po Woon Primary School |
Free field |
NM5 |
Village House in Tin Sum |
Free field |
NM6 |
House No. 1, Sha Lo Wan |
Free field |
Note:
(1)
As described in Section 4.3.3 of the Manual, noise monitoring at NM2
will only commence after occupation of the future Tung Chung West Development.
(2) According to Section 4.3.3 of the
Manual, the noise monitoring at NM3A was temporarily suspended starting from 1
September 2018 and would be resumed with the completion of the Tung Chung East
Development.
In accordance with the Manual, baseline noise levels at the
noise monitoring stations were established as presented in the Baseline
Monitoring Report. The Action and Limit Levels of the noise monitoring
stipulated in the EM&A programme for triggering the relevant investigation
and follow-up procedures under the programme are provided in Table 3.2.
Table 3.2: Action and Limit Levels
for Noise Monitoring
Monitoring Stations |
Time Period |
Action Level |
Limit Level, Leq(30mins) dB(A) |
NM1A, NM2, NM3A, NM4, NM5 and NM6 |
0700-1900 hours on normal weekdays |
When one documented complaint is received from any one of the sensitive receivers |
75dB(A)(1) |
Note:
(1)
The Limit Level for NM4 is reduced to 70dB(A) for being an educational
institution. During school examination period, the Limit Level is further
reduced to 65dB(A).
Noise monitoring was performed
using sound level meter at each designated monitoring station. The sound
level meters deployed comply with the International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic
calibrator was used to check the sound level meters by a known sound pressure
level for field measurement. Details of equipment used in the reporting
period are given in Table 3.3.
Table
3.3: Noise Monitoring Equipment
Equipment |
Brand and Model |
Last Calibration Date |
Calibration Certificate Provided in |
Integrated Sound Level Meter |
NTi XL2 (Serial No. A2A-14829-E0) |
14 Jul 2019 |
Monthly EM&A Report No. 43, Appendix D |
Rion NL-52 (Serial No. 01287679) |
21 Sep 2019 |
Monthly EM&A Report No. 45, Appendix D |
|
Acoustic Calibrator |
Casella CEL-120/1 (Serial No. 2383737) |
21 Sep 2019 |
Monthly EM&A Report No. 45, Appendix D |
Castle GA607 (Serial No. 040162) |
14 Jul 2019 |
Monthly EM&A Report No. 43, Appendix D |
The monitoring procedures involved in the noise monitoring
can be summarised as follows:
a. The sound level meter was set on a tripod at
least a height of 1.2m above the ground for free-field measurements at
monitoring stations NM1A, NM4, NM5 and NM6. A correction of +3dB(A) was applied
to the free field measurements.
b. Façade measurements were made at the
monitoring station NM3A.
c. Parameters such as frequency weighting,
time weighting and measurement time were set.
d. Prior to and after each noise measurement,
the meter was calibrated using the acoustic calibrator. If the difference
in the calibration level before and after measurement was more than 1dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
e. During the monitoring period, Leq,
L10 and L90 were recorded. In addition, site
conditions and noise sources were recorded on a record sheet.
f. Noise measurement results were
corrected with reference to the baseline monitoring levels.
g. Observations were recorded when high
intrusive noise (e.g. dog barking, helicopter noise) was observed during the
monitoring.
The maintenance and calibration procedures are summarised
below:
a. The microphone head of the sound level meter
was cleaned with soft cloth at regular intervals.
b. The meter and calibrator were sent to the
supplier or laboratory accredited under Hong Kong Laboratory Accreditation
Scheme (HOKLAS) to check and calibrate at yearly intervals.
Calibration
certificates of the sound level meters and acoustic calibrators used in the
noise monitoring listed in Table 3.3
are valid in the reporting period.
The noise monitoring schedule involved in
the reporting period is provided in Appendix B.
The noise monitoring results in
the reporting period are summarised in Table 3.4. Detailed
impact monitoring results are presented in Appendix C.
Table 3.4: Summary of Construction
Noise Monitoring Results
Monitoring Station |
Noise Level Range, dB(A) Leq (30 mins) |
Limit Level, dB(A) Leq (30 mins) |
NM1A(1) |
68 - 72 |
75 |
NM4(1) |
61 - 66 |
70(2) |
NM5(1) |
53 - 67 |
75 |
NM6(1) |
62 - 74 |
75 |
Notes:
(1)
+3dB(A) Façade correction included;
(2)
Reduced to 65dB(A) during school examination periods at NM4. No school
examination took place during this reporting period.
No complaints were received from
any sensitive receiver that triggered the Action Level. All monitoring results
were also within the corresponding Limit Levels at all monitoring stations in
the reporting period.
As the construction activities were far away from the monitoring stations, major sources of noise dominating the monitoring stations observed during the construction noise impact monitoring were traffic noise near NM1A and aircraft noise near NM6 during this reporting period. It is considered that the monitoring work during the reporting period was effective and there was no adverse impact attributable to the Project activities.
Water
quality monitoring of DO, pH, temperature, salinity, turbidity, suspended
solids (SS), total alkalinity, chromium, and nickel was conducted three days
per week, at mid-ebb and mid-flood tides, at a total of 23 water quality
monitoring stations, comprising 12 impact (IM) stations, 8 sensitive receiver
(SR) stations and 3 control (C) stations in the vicinity of water quality
sensitive receivers around the airport island in accordance with the Manual. The purpose of water quality monitoring at the IM stations
is to promptly capture any potential water quality impact from the Project
before it could become apparent at sensitive receivers (represented by the SR
stations). Table 4.1
describes the details of the monitoring stations. Figure 4.1 shows the locations of the
monitoring stations.
Table 4.1: Monitoring Locations and
Parameters of Impact Water Quality Monitoring
Monitoring Station |
Description |
Coordinates |
Parameters |
|
|
|
Easting |
Northing |
|
C1 |
Control Station |
804247 |
815620 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
DCM Parameters Total Alkalinity, Heavy Metals(2) |
C2 |
Control Station |
806945 |
825682 |
|
C3(3) |
Control Station |
817803 |
822109 |
|
IM1 |
Impact Station |
807132 |
817949 |
|
IM2 |
Impact Station |
806166 |
818163 |
|
IM3 |
Impact Station |
805594 |
818784 |
|
IM4 |
Impact Station |
804607 |
819725 |
|
IM5 |
Impact Station |
804867 |
820735 |
|
IM6 |
Impact Station |
805828 |
821060 |
|
IM7 |
Impact Station |
806835 |
821349 |
|
IM8 |
Impact Station |
808140 |
821830 |
|
IM9 |
Impact Station |
808811 |
822094 |
|
IM10 |
Impact Station |
809794 |
822385 |
|
IM11 |
Impact Station |
811460 |
822057 |
|
IM12 |
Impact Station |
812046 |
821459 |
|
SR1A(1) |
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) Seawater Intake for cooling |
812660 |
819977 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS |
SR2(3) |
Planned marine park / hard corals at The Brothers / Tai Mo To |
814166 |
821463 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
DCM Parameters Total Alkalinity, Heavy Metals(2)(4) |
SR3 |
Sha Chau and Lung Kwu Chau Marine Park / fishing and spawning grounds in North Lantau |
807571 |
822147 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
|
SR4A |
Sha Lo Wan |
807810 |
817189 |
|
SR5A |
San Tau Beach SSSI |
810696 |
816593 |
|
SR6A(5) |
Tai Ho Bay, Near Tai Ho Stream SSSI |
814739 |
817963 |
|
SR7 |
Ma Wan Fish Culture Zone (FCZ) |
823742 |
823636 |
|
SR8(6) |
Seawater Intake for cooling at Hong Kong International Airport (East) |
811623 |
820390 |
Notes:
(1)
With the operation of HKBCF, water quality monitoring at SR1A station
was commenced on 25 October 2018. To better reflect the water quality in the
immediate vicinity of the intake, the monitoring location of SR1A has been
shifted closer to the intake starting from 5 January 2019.
(2)
Details of selection criteria for the two
heavy metals for regular DCM monitoring refer to the Detailed Plan on Deep
Cement Mixing available on the dedicated 3RS website (http://env.threerunwaysystem.com/en/ep-submissions.html). DCM specific water quality monitoring parameters
(total alkalinity and heavy metals) were only conducted at C1 to C3, SR2, and
IM1 to IM12.
(3)
According to the Baseline
Water Quality Monitoring Report, C3 station is not adequately representative as
a control station of impact/ SR stations during the flood tide. The control
reference has been changed from C3 to SR2 from 1 September 2016 onwards.
(4)
Total alkalinity and heavy
metals results are collected at SR2 as a control station for regular DCM
monitoring.
(5)
As the access to SR6 was
obstructed by the construction activities and temporary structures for Tung
Chung New Town Extension, the monitoring location has been relocated to SR6A
starting from 8 August 2019.
(6) The monitoring location for SR8 is subject to
further changes due to silt curtain arrangements and the progressive relocation
of this seawater intake.
In accordance with the Manual,
baseline water quality levels at the above-mentioned representative water
quality monitoring stations were established as presented in the Baseline Water
Quality Monitoring Report. The
Action and Limit Levels of general water quality monitoring and regular DCM
monitoring stipulated in the EM&A programme for triggering the relevant
investigation and follow-up procedures under the programme are provided in Table 4.2.
The control and impact stations during ebb tide and flood tide for general
water quality monitoring and regular DCM monitoring are presented in Table 4.3.
Table 4.2: Action and Limit Levels
for General Water Quality Monitoring and Regular DCM Monitoring
Parameters |
Action Level (AL) |
Limit Level (LL) |
|||
Action and Limit Levels for general water quality monitoring and regular DCM monitoring (excluding SR1A & SR8) |
|||||
General Water Quality Monitoring |
DO in mg/L (Surface, Middle & Bottom) |
Surface and Middle 4.5mg/L |
Surface and Middle 4.1mg/L 5mg/L for Fish Culture Zone (SR7) only |
||
Bottom 3.4mg/L |
Bottom 2.7mg/L |
||||
Suspended Solids (SS) in mg/L |
23 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
37 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
|
Turbidity in NTU |
22.6 |
36.1 |
|||
Regular DCM Monitoring |
Total Alkalinity in ppm |
95 |
99 |
||
Representative Heavy Metals for regular DCM monitoring (Chromium) in µg/L |
0.2 |
0.2 |
|||
Representative Heavy Metals for regular DCM monitoring (Nickel) in µg/L |
3.2 |
|
3.6 |
|
|
Action and Limit Levels SR1A |
|
|
|
||
SS (mg/l) |
33 |
|
42 |
|
|
Action and Limit Levels SR8 |
|
|
|
|
|
SS (mg/l) |
52 |
|
60 |
|
Notes:
(1)
For DO measurement, non-compliance occurs when monitoring result is
lower than the limits.
(2)
For parameters other than DO, non-compliance of water quality results
when monitoring results is higher than the limits.
(3)
Depth-averaged results are used unless specified otherwise.
(4)
Details of selection criteria
for the two heavy metals for regular DCM monitoring refer to the Detailed Plan
on Deep Cement Mixing available on the dedicated 3RS website (http://env.threerunwaysystem.com/en/ep-submissions.html)
(5) The Action and Limit Levels for the
two representative heavy metals chosen will be the same as that for the
intensive DCM monitoring.
Table
4.3: The Control and Impact Stations during Flood Tide and Ebb Tide for General
Water Quality Monitoring and Regular DCM Monitoring
Control Station |
Impact Stations |
Flood Tide |
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
SR2(1) |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6A, SR8 |
Ebb Tide |
|
C1 |
SR4A, SR5A, SR6A |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
Note:
(1) As per findings of Baseline Water Quality
Monitoring Report, the control reference has been changed from C3 to SR2 from 1
September 2016 onwards.
Table 4.4 summarises
the equipment used in the reporting period for monitoring of specific water
quality parameters under the water quality monitoring programme.
Table 4.4: Water Quality Monitoring
Equipment
Brand and Model |
Last Calibration Date |
Calibration Certificate Provided in |
|
Multifunctional Meter (measurement of DO, pH, temperature, salinity and turbidity) |
YSI 6920V2 (Serial No. 0001C6A7) |
28 Oct 2019 |
Monthly EM&A Report No. 46, Appendix E |
YSI 6920V2 (Serial No. 00019CB2) |
28 Oct 2019 |
||
YSI ProDSS (Serial No. 17H105557) |
27 Sep 2019 |
Monthly EM&A Report No. 45, Appendix D |
|
YSI ProDSS (Serial No. 16H104233) |
27 Sep 2019 |
||
Digital Titrator (measurement of total alkalinity) |
Titrette Digital Burette 50ml Class A (Serial No. 10N64701) |
9 Sep 2019 |
Monthly EM&A Report No. 45, Appendix D |
Other equipment used as part of
the impact water quality monitoring programme are listed in Table 4.5.
Table 4.5: Other Monitoring Equipment
Equipment |
Brand and Model |
Water Sampler |
Van Dorn Water Sampler |
Positioning Device (measurement of GPS) |
Garmin eTrex Vista HCx |
Current Meter (measurement of current speed and direction, and water depth) |
Sontek HydroSurveyor |
Water
quality monitoring samples were taken at three depths (at 1m below surface, at
mid-depth, and at 1m above bottom) for locations with water depth >6m. For
locations with water depth between 3m and 6m, water samples were taken at two
depths (surface and bottom). For locations with water depth <3m, only the mid-depth
was taken. Duplicate water samples were taken and analysed.
The water samples for all
monitoring parameters were collected, stored, preserved and analysed
according to the Standard Methods, APHA 22nd ed. and/or other
methods as agreed by the EPD. In-situ measurements at monitoring locations
including temperature, pH, DO, turbidity, salinity, alkalinity and water depth
were collected by equipment listed in Table 4.4 and Table 4.5.
Water samples for heavy metals and SS analysis were stored in high density
polythene bottles with no preservative added, packed in ice (cooled to 4ºC
without being frozen), delivered to the laboratory within 24 hours of
collection.
Calibration of In-situ Instruments
Wet bulb calibration for a DO meter
was carried out before commencement of monitoring and after completion of all
measurements each day. Calibration was not conducted at each monitoring
location as daily calibration is adequate for the type of DO meter employed. A
zero check in distilled water was performed with the turbidity probe at least
once per monitoring day. The probe was then calibrated with a solution of known
NTU. In addition, the turbidity probe was calibrated at least twice per month
to establish the relationship between turbidity readings (in NTU) and levels of
SS (in mg/L). Accuracy check of the digital titrator was performed at
least once per monitoring day.
Calibration certificates of the
monitoring equipment used in the reporting period listed in Table 4.4
are still valid.
Analysis of
SS and heavy metals have been carried out by a HOKLAS accredited laboratory,
ALS Technichem (HK) Pty Ltd (Reg. No. HOKLAS 066). Sufficient water samples
were collected at all the monitoring stations for carrying out the laboratory
SS and heavy metals determination. The SS and heavy metals determination works
were started within 24 hours after collection of the water samples. The
analysis of SS and heavy metals have followed the standard methods summarised
in Table 4.6.
The QA/QC procedures for laboratory measurement/ analysis of SS and heavy
metals were presented in Appendix F of the Construction Phase Monthly EM&A
Report No.8.
Table 4.6: Laboratory Measurement/ Analysis of
SS and Heavy Metals
Parameters |
Instrumentation |
Analytical Method |
Reporting Limit |
SS |
Analytical Balance |
APHA 2540D |
2mg/L |
Heavy Metals |
|
|
|
Chromium (Cr) |
ICP-MS |
USEPA 6020A |
0.2µg/L |
Nickel (Ni) |
ICP-MS |
USEPA 6020A |
0.2µg/L |
The water quality monitoring schedule for the reporting period
is updated and provided in Appendix B.
The water quality
monitoring results for DO, turbidity, total alkalinity, nickel, and chromium
obtained during the reporting period were within their corresponding Action and
Limit Level. The detailed
monitoring results are presented in Appendix C.
For SS, one of
the testing results triggered the corresponding Action Level, and investigation
was conducted accordingly.
Table 4.7 presents
the summary of the SS compliance status at IM and SR stations during mid-ebb
tide for the reporting period.
Table 4.7: Summary of SS Compliance Status (Mid-Ebb
Tide)
Legend: |
|
|
The monitoring results were within the corresponding Action and Limit Levels |
|
Monitoring result triggered the Action Level at monitoring station located upstream of the Project based on dominant tidal flow |
|
Upstream station with respect to the Project during the respective tide based on dominant tidal flow |
Action Level was triggered on 16
November 2019. The case occurred at monitoring station upstream of the Project
during respective tide and would unlikely be affected by the Project.
During the reporting period, it
is noted that the vast majority of monitoring results were within their
corresponding Action and Limit Levels, while only one result triggered the
corresponding Action Level, and investigation was conducted accordingly.
Based on the investigation
findings, the result that triggered the corresponding Action Level was not due
to the Project. Therefore, the Project did not cause adverse impact at the
water quality sensitive receivers. All required actions under the Event and
Action Plan were followed. The case appeared to be due to natural fluctuation
or other sources not related to the Project.
Nevertheless, as part of the
EM&A programme, the construction methods and mitigation measures for water
quality will continue to be monitored and opportunities for further enhancement
will continue to be explored and implemented where possible, to strive for
better protection of water quality and the marine environment.
In the meantime, the contractors were reminded to implement and maintain all mitigation measures during weekly site inspection and regular environmental management meetings. These include maintaining mitigation measures properly for reclamation works including DCM works, marine filling, and seawall construction as recommended in the Manual.
In accordance with the Manual,
the waste generated from construction activities was audited once per week to
determine if wastes are being managed in accordance with the Waste Management
Plan (WMP) prepared for the Project, contract-specific WMP, and any statutory
and contractual requirements. All aspects of waste management including waste
generation, storage, transportation and disposal were assessed during the
audits.
The Action and Limit Levels of
the construction waste are provided in Table 5.1.
Table 5.1: Action and Limit Levels
for Construction Waste
Monitoring Stations |
Action Level |
Limit Level |
Construction Area |
When one valid documented complaint is received |
Non-compliance of the WMP, contract-specific WMPs, any statutory and contractual requirements |
Weekly monitoring on all works
contracts were carried out by the ET to check and monitor the implementation of
proper waste management practices during the construction phase.
Recommendations made included
provision and maintenance of proper chemical waste storage area, as well as
handling, segregation, and regular disposal of general refuse. The contractors
had taken actions to implement the recommended measures.
Based on updated information
provided by contractors, construction waste generated in the reporting period
is summarised in Table 5.2.
There were no complaints,
non-compliance of the WMP, contract-specific WMPs, statutory and contractual
requirements that triggered Action and Limit Levels in the reporting period.
Table 5.2: Construction Waste
Statistics
|
C&D(1) Material Stockpiled for Reuse or Recycle (m3) |
C&D Material Reused in the Project (m3) |
C&D Material Reused in other Projects (m3) |
C&D Material Transferred to Public Fill (m3) |
Chemical Waste (kg) |
Chemical Waste (L) |
General Refuse (tonne) |
November 2019(2)(3) |
1,403 |
22,875 |
3,875 |
3,380 |
90 |
6,600 |
680 |
Notes: (1) C&D refers to Construction and Demolition. (2) Metals, paper and/or plastics were recycled in the reporting period. (3) The data was based on the information provided by contractors up to the submission date of this Monthly EM&A Report, and might be updated in the forthcoming Monthly EM&A Report. |
|||||||
|
In
accordance with the Manual, CWD monitoring by small vessel line-transect
survey supplemented by land-based theodolite tracking survey and passive
acoustic monitoring should be conducted during construction phase.
The small vessel line-transect
survey should be conducted at a frequency of two full surveys per month, while
land-based theodolite tracking survey should be conducted at a frequency of one
day per month per station at Sha Chau (SC) and Lung Kwu Chau (LKC) during the
construction phase as stipulated in the Manual. Supplemental theodolite
tracking survey of one additional day has also been conducted at LKC, i.e. in
total twice per month at the LKC station.
The Action and Limit Levels for
CWD monitoring were formulated by the action response approach using the
running quarterly dolphin encounter rates STG and ANI derived from the baseline
monitoring data, as presented in the CWD Baseline Monitoring Report. The
derived values of Action and Limit Levels for CWD monitoring were summarised in
Table 6.1.
Table 6.1: Derived Values of Action and Limit
Levels for Chinese White Dolphin Monitoring
|
NEL, NWL, AW, WL and SWL as a Whole |
Action Level(3) |
Running quarterly(1) STG < 1.86 & ANI < 9.35 |
Limit Level(3) |
Two consecutive running quarterly(2) (3-month) STG < 1.86 & ANI < 9.35 |
Notes: (referring to the baseline monitoring report) (1) Action Level – running quarterly STG & ANI will be calculated from the three preceding survey months. (2) Limit Level – two consecutive running quarters mean both the running quarterly encounter rates of the preceding month and the running quarterly encounter rates of this month. (3) Action Level and/or Limit Level will be triggered if both STG and ANI fall below the criteria. |
Small
vessel line-transect surveys were conducted along the transects covering
Northeast Lantau (NEL), Northwest Lantau (NWL), Airport West (AW), West Lantau
(WL) and Southwest Lantau (SWL) areas as proposed in the Manual, which are
consistent with the Agriculture, Fisheries and Conservation Department (AFCD)
long-term monitoring programme (except the addition of AW). The AW transect has
not been previously surveyed in the AFCD programme due to the restrictions of
HKIA Approach Area, nevertheless, this transect was established during the EIA
of the 3RS Project and refined in the Manual with the aim to collect project
specific baseline information within the HKIA Approach Area to fill the data
gap that was not covered by the AFCD programme. This also provided a larger
sample size for estimating the density, abundance and patterns of movements in
the broader study area of the project.
The planned vessel survey
transect lines follow the waypoints set for construction phase monitoring as
proposed in the Manual and depicted in Figure 6.1 with the waypoint coordinates
of all transect lines given in Table
6.2, which are subject to on-site refinement based on
the actual survey conditions and constraints.
Table 6.2:
Coordinates of Transect Lines in NEL, NWL, AW, WL and SWL Survey Areas
Waypoint |
Easting |
Northing |
Waypoint |
Easting |
Northing |
NEL |
|||||
1S |
813525 |
820900 |
6N |
818568 |
824433 |
1N |
813525 |
824657 |
7S |
819532 |
821420 |
2S |
814556 |
818449 |
7N |
819532 |
824209 |
2N |
814559 |
824768 |
8S |
820451 |
822125 |
3S |
815542 |
818807 |
8N |
820451 |
823671 |
3N |
815542 |
824882 |
9S |
821504 |
822371 |
4S |
816506 |
819480 |
9N |
821504 |
823761 |
4N |
816506 |
824859 |
10S |
822513 |
823268 |
5S |
817537 |
820220 |
10N |
822513 |
824321 |
5N |
817537 |
824613 |
11S |
823477 |
823402 |
6S |
818568 |
820735 |
11N |
823477 |
824613 |
NWL |
|||||
1S |
804671 |
814577 |
5S |
808504 |
821735 |
1N |
804671 |
831404 |
5N |
808504 |
828602 |
2Sb |
805475 |
815457 |
6S |
809490 |
822075 |
2Nb |
805476 |
818571 |
6N |
809490 |
825352 |
2Sa |
805476 |
820770 |
7S |
810499 |
822323 |
2Na |
805476 |
830562 |
7N |
810499 |
824613 |
3S |
806464 |
821033 |
8S |
811508 |
821839 |
3N |
806464 |
829598 |
8N |
811508 |
824254 |
4S |
807518 |
821395 |
9S |
812516 |
821356 |
4N |
807518 |
829230 |
9N |
812516 |
824254 |
AW |
|||||
1W |
804733 |
818205 |
2W |
805045 |
816912 |
1E |
806708 |
818017 |
2E |
805960 |
816633 |
WL |
|||||
1W |
800600 |
805450 |
7W |
800400 |
811450 |
1E |
801760 |
805450 |
7E |
802400 |
811450 |
2W |
800300 |
806450 |
8W |
800800 |
812450 |
2E |
801750 |
806450 |
8E |
802900 |
812450 |
3W |
799600 |
807450 |
9W |
801500 |
813550 |
3E |
801500 |
807450 |
9E |
803120 |
813550 |
4W |
799400 |
808450 |
10W |
801880 |
814500 |
4E |
801430 |
808450 |
10E |
803700 |
814500 |
5W |
799500 |
809450 |
11W |
802860 |
815500 |
5E |
801300 |
809450 |
12S/11E |
803750 |
815500 |
6W |
799800 |
810450 |
12N |
803750 |
818500 |
6E |
801400 |
810450 |
|
|
|
SWL |
|||||
1S |
802494 |
803961 |
6S |
807467 |
801137 |
1N |
802494 |
806174 |
6N |
807467 |
808458 |
2S |
803489 |
803280 |
7S |
808553 |
800329 |
2N |
803489 |
806720 |
7N |
808553 |
807377 |
3S |
804484 |
802509 |
8S |
809547 |
800338 |
3N |
804484 |
807048 |
8N |
809547 |
807396 |
4S |
805478 |
802105 |
9S |
810542 |
800423 |
4N |
805478 |
807556 |
9N |
810542 |
807462 |
5S |
806473 |
801250 |
10S |
811446 |
801335 |
5N |
806473 |
808458 |
10N |
811446 |
809436 |
Land-based
theodolite tracking survey stations were set up at two locations, one facing
east/south/west on the southern slopes of Sha Chau (SC), and the other facing
north/northeast/northwest at Lung Kwu Chau (LKC). The stations (D and E)
are depicted in Figure 6.2 and shown in Table 6.3
with position coordinates, height of station and approximate distance of
consistent theodolite tracking capabilities for CWD.
Table 6.3:
Land-based Theodolite Survey Station Details
Stations |
Location |
Geographical Coordinates |
Station Height (m) |
Approximate Tracking Distance (km) |
D |
Sha Chau (SC) |
22° 20’ 43.5” N 113° 53’ 24.66” E |
45.66 |
2 |
E |
Lung Kwu Chau (LKC) |
22° 22’ 44.83” N 113° 53’ 0.2” E |
70.40 |
3 |
Small vessel line-transect
surveys provided data for density and abundance estimation and other
assessments using distance-sampling methodologies, specifically, line-transect
methods.
The surveys involved small vessel
line-transect data collection and have been designed to be similar to, and
consistent with, previous surveys for the AFCD for their long-term monitoring
of small cetaceans in Hong Kong. The survey was designed to provide systematic,
quantitative measurements of density, abundance and habitat use.
As mentioned in Section 6.2.1,
the transects covered NEL, NWL covering the AW, WL and SWL areas as proposed in
the Manual and are consistent with the AFCD long-term monitoring programme
(except AW). There are two types of transect lines:
● Primary transect lines: the
parallel and zigzag transect lines as shown in Figure 6.1; and
● Secondary transect lines:
transect lines connecting between the primary transect lines and going around
islands.
All data collected on both
primary and secondary transect lines were used for analysis of sighting
distribution, group size, activities including association with fishing boat,
and mother-calf pairs. Only on-effort data collected under conditions of
Beaufort 0-3 and visibility of approximately 1200 m or beyond were used for
analysis of the CWD encounter rates.
A 15-20m vessel with a flying
bridge observation platform about 4 to 5m above water level and unobstructed
forward view, and a team of three to four observers were deployed to undertake
the surveys. Two observers were on search effort at all times when
following the transect lines with a constant speed of 7 to 8 knots (i.e. 13 to
15km per hour), one using 7X handheld binoculars and the other using unaided
eyes and recording data.
During on-effort survey periods,
the survey team recorded effort data including time, position (waypoints),
weather conditions (Beaufort sea state and visibility) and distance travelled
in each series with assistance of a handheld GPS device. The GPS device also
continuously and automatically logged data including time, position (latitude
and longitude) and vessel speed throughout the entire survey.
When CWDs were seen, the survey
team was taken off-effort, the dolphins were approached and photographed for
photo-ID information (using a Canon 7D [or similar] camera and long 300 mm+
telephoto lens), then followed until they were lost from view. At that
point, the boat returned (off effort) to the survey line at the closest point after
obtaining photo records of the dolphin group and began to survey on effort
again.
Focal follows of dolphins would
be used for providing supplementary information only where practicable (i.e.
when individual dolphins or small stable groups of dolphins with at least one
member that could be readily identifiable with unaided eyes during observations
and weather conditions are favourable). These would involve the boat following
(at an appropriate distance to minimise disturbance) an identifiable individual
dolphin for an extended period of time, and collecting detailed data on its
location, behaviour, response to vessels, and associates.
CWDs can be identified by their unique features
like presence of scratches, nick marks, cuts, wounds, deformities of
their dorsal fin and distinguished colouration and spotting patterns.
When CWDs were observed, the survey team was
taken off-effort, the dolphins were approached and photographed for
photo-ID information (using a Canon 7D [or similar] camera and long 300 mm+
telephoto lens). The survey team attempted to photo both sides of every single
dolphin in the group as the colouration and spotting pattern on both sides may
not be identical. The photos were taken at the highest available resolution and
stored on Compact Flash memory cards for transferring into a computer.
All photos taken were initially
examined to sort out those containing potentially identifiable individuals.
These sorted-out images would then be examined in detail and compared to the
CWD photo-identification catalogue established for 3RS during the baseline
monitoring stage.
Land-based theodolite tracking survey obtains
fine-scale information on the time of day and movement patterns of the
CWDs. A digital theodolite (Sokkia/Sokkisha Model DT5 or similar
equipment) with 30-power magnification and 5-s precision was used to obtain the vertical and horizontal angle of each
dolphin and vessel position. Angles
were converted to geographic coordinates (latitude and longitude) and
data were recorded using Pythagoras software, Version 1.2. This
method delivers precise positions of multiple
spatially distant targets in a short period of time. The
technique is fully non-invasive, and allows for time and cost-effective
descriptions of dolphin habitat use patterns at all times of daylight.
Three surveyors (one theodolite
operator, one computer operator, and one observer) were involved in each survey.
Observers searched for dolphins using unaided eyes and handheld binoculars
(7X50). Theodolite tracking sessions were initiated whenever an individual CWD
or group of CWDs was located. Where possible, a distinguishable
individual was selected, based on colouration, within the group. The
focal individual was then continuously tracked via the theodolite, with a
position recorded each time the dolphin surfaced. In case an individual could
not be positively distinguished from other members, the group was tracked by
recording positions based on a central point within the group whenever the CWD
surfaced. Tracking continued until animals were lost from view; moved beyond
the range of reliable visibility (>1-3km, depending on station height); or
environmental conditions obstructed visibility (e.g., intense haze, Beaufort
sea state >4, or sunset), at which time the research effort was
terminated. In addition to the tracking of CWD, all vessels that moved
within 2-3km of the station were tracked, with effort made to obtain at least
two positions for each vessel.
Theodolite tracking included
focal follows of CWD groups and vessels. Priority was given to tracking
individual or groups of CWD. The survey team also attempted to track all
vessels moving within 1 km of the focal CWD.
Within this reporting period, two complete sets
of small vessel line-transect surveys were conducted on the 7, 8, 11, 12, 13,
21, 22 and 29 November 2019, covering all transects in NEL, NWL, AW, WL and SWL
survey areas for twice.
A total of around 454.80 km of survey effort
was collected from these surveys and around 96.7% of the survey effort was
being conducted under favourable weather condition (i.e. Beaufort Sea State 3
or below with favourable visibility). Details of the survey effort are given in
Appendix C.
Sighting
Distribution
In November 2019, 12 sightings with 26 dolphins
were sighted. Amongst these sightings, 11 sightings with 24 dolphins are
on-effort sightings under favourable weather condition (i.e. Beaufort Sea State
3 or below with favourable visibility). Details of cetacean sightings are
presented in Appendix C.
Distribution of all CWD sightings recorded in
November 2019 is illustrated in Figure 6.3. In NWL including the AW
transect, the CWD sightings were distributed at the southwestern part of the
survey area, the central part of SCLKCMP and also the waters between Lung Kwu
Chau and Lung Kwu Tan. In WL, CWD sightings were recorded from Tai O to Peaked
Hill. In SWL, CWD sightings were located at the coastal waters around Fan Lau
Tung Wan and Lo Kei Wan. No sightings of CWD were recorded in NEL or in close
vicinity of the 3RS works area.
Figure 6.3:
Sightings Distribution of Chinese White Dolphins
Encounter Rate
Two types of dolphin encounter rates were
calculated based on the data from November 2019. They included the number of
dolphin sightings per 100 km survey effort (STG) and total number of dolphins
per 100 km survey effort (ANI) in the whole survey area (i.e. NEL, NWL, AW, WL
and SWL). In the calculation of dolphin encounter rates, only survey data
collected under favourable weather condition (i.e. Beaufort Sea State 3 or
below with favourable visibility) were used. The formulae used for calculation
of the encounter rates are shown below:
Encounter
Rate by Number of Dolphin Sightings (STG)
Encounter
Rate by Number of Dolphins (ANI)
(Notes: Only data
collected under Beaufort 3 or below condition were used)
In November 2019, a total of around 439.80 km
of survey effort were conducted under Beaufort Sea State 3 or below with
favourable visibility, whilst a total number of 11 on-effort sightings with 24
dolphins were sighted under such condition. Calculation of the encounter rates
in November 2019 are shown in Appendix C.
For the running quarter of the reporting period
(i.e., from September 2019 to November 2019), a total of around 1315.31 km of
survey effort were conducted under Beaufort Sea State 3 or below with
favourable visibility, whilst a total number of 45 on-effort sightings and a
total number of 153 dolphins from on-effort sightings were obtained under such
condition. Calculation of the running quarterly encounter rates are shown in Appendix C.
The STG and ANI of CWD in the whole survey area
(i.e. NEL, NWL, AW, WL and SWL) during the month of November 2019 and during the
running quarter are presented in Table
6.4 below and compared
with the Action Level. The running quarterly encounter rates STG and ANI did
not trigger Action Level.
Table
6.4: Comparison of CWD Encounter Rates of the Whole Survey Area with
Action Levels
|
Encounter Rate (STG) |
Encounter Rate (ANI) |
November 2019 |
2.50 |
5.46 |
Running Quarter from September 2019 to November 2019(1) |
3.42 |
11.63 |
Action Level |
Running quarterly(1) STG < 1.86 & ANI < 9.35 |
|
Note: (1) Running quarterly encounter rates STG & ANI were calculated from data collected in the reporting period and the two preceding survey months, i.e. the data from September 2019 to November 2019, containing six sets of transect surveys for all monitoring areas. Action Level will be triggered if both STG and ANI fall below the criteria. |
Group Size
In November 2019, 12 groups with 26 dolphins
were sighted, and the average group size of CWDs was 2.2 dolphins per group.
Sightings with small group size (i.e. 1-2 dolphins) were dominant. No CWD
sighting with large group size (i.e. 10 or more dolphins) was recorded.
Activities
and Association with Fishing Boats
Two sightings of CWDs were recorded engaging in
feeding activities in November 2019. No CWD sightings were observed in
association with operating fishing boat in the reporting month.
Mother-calf Pair
In November 2019, there was no sighting of CWD
with the presence of mother-and-calf pair.
In November 2019, a total number of 20
different CWD individuals were identified for totally 21 times. A summary of photo
identification works is presented in Table 6.5. Representative photos of
these individuals are given in Appendix C.
Table 6.5: Summary of Photo
Identification
Individual ID |
Date of Sighting (dd-mmm-yy) |
Sighting Group No. |
Area |
|
Individual ID |
Date of Sighting (dd-mmm-yy) |
Sighting Group No. |
Area |
NLMM004 |
11-Nov-19 |
3 |
NWL |
|
SLMM049 |
22-Nov-19 |
6 |
SWL |
NLMM013 |
11-Nov-19 |
3 |
NWL |
|
SLMM052 |
12-Nov-19 |
1 |
WL |
NLMM019 |
11-Nov-19 |
1 |
NWL |
|
SLMM053 |
22-Nov-19 |
4 |
WL |
|
22-Nov-19 |
4 |
WL |
|
SLMM060 |
21-Nov-19 |
2 |
SWL |
NLMM020 |
11-Nov-19 |
1 |
NWL |
|
WLMM001 |
22-Nov-19 |
2 |
WL |
SLMM003 |
12-Nov-19 |
1 |
WL |
|
WLMM006 |
22-Nov-19 |
2 |
WL |
SLMM011 |
11-Nov-19 |
1 |
NWL |
|
WLMM008 |
22-Nov-19 |
5 |
WL |
SLMM012 |
21-Nov-19 |
4 |
SWL |
|
WLMM029 |
22-Nov-19 |
2 |
WL |
SLMM028 |
22-Nov-19 |
1 |
WL |
|
WLMM056 |
21-Nov-19 |
4 |
SWL |
SLMM031 |
21-Nov-19 |
4 |
SWL |
|
WLMM063 |
22-Nov-19 |
2 |
WL |
SLMM037 |
12-Nov-19 |
1 |
WL |
|
|
|
|
|
Survey
Effort
Land-based theodolite tracking
surveys were conducted at LKC on 12 and 21 November 2019 and at SC on 28 November 2019, with a
total of three days of land-based theodolite tracking survey effort
accomplished in this reporting period. Two CWD groups were tracked at LKC
station during the surveys. Information of survey effort and CWD groups sighted
during these land-based theodolite tracking surveys are presented in Table 6.6.
Details of the survey effort and CWD groups tracked are presented in Appendix C. The first sighting locations
of CWD groups tracked at LKC station during land-based theodolite tracking surveys
in November 2019 were depicted in Figure 6.4. No CWD group was sighted
from SC station in this reporting month.
Table 6.6: Summary of Survey Effort and CWD Group of
Land-based Theodolite Tracking
Land-based Station |
|
No. of Survey Sessions |
Survey Effort (hh:mm) |
No. of CWD Groups Sighted |
CWD Group Sighting per Survey Hour |
Lung Kwu Chau |
|
2 |
12:00 |
2 |
0.17 |
Sha Chau |
|
1 |
6:00 |
0 |
0 |
TOTAL |
|
3 |
18:00 |
2 |
0.11 |
Figure 6.4:
Plots of First Sightings of All CWD Groups obtained from Land-based Stations
Underwater acoustic monitoring using Passive Acoustic
Monitoring (PAM) should be undertaken during land formation related
construction works. In this reporting period, the Ecological Acoustic Recorder
(EAR) was remained underwater and positioned at south of Sha Chau Island inside
the SCLKCMP with 20% duty cycle (Figure 6.5). The EAR deployment is
generally for 6 weeks prior to data retrieval for analysis. Acoustic data is
reviewed to give an indication of CWDs occurrence patterns and to obtain
anthropogenic noise information simultaneously. Analysis (by a specialised team
of acousticians) involved manually browsing through every acoustic recording
and logging the occurrence of dolphin signals. All data will be re-played by
computer as well as listened to by human ears for accurate assessment of
dolphin group presence. As the period of data collection and analysis takes
more than four months, PAM results could not be reported in monthly intervals
but report for supplementing the annual CWD monitoring analysis.
During the reporting period, silt
curtains were in place by the contractor for marine filling , in which dolphin
observers were deployed by contractor in accordance with the MMWP. Overall, 4
to 8 dolphin observation stations and teams of at least two dolphin observers
were deployed by the contractors for continuous monitoring of the DEZ for DCM
works and seawall construction in accordance with the DEZ Plan. Trainings for
the proposed dolphin observers on the implementation of MMWP and DEZ monitoring
were provided by the ET prior to the aforementioned works, with a cumulative
total of 679 individuals being trained and the training records kept by the ET.
From the contractors’ MMWP observation records, no dolphin or other marine
mammals were observed within or around the silt curtains. As for DEZ monitoring
records, no dolphin or other marine mammals were observed within or around the
DEZs in this reporting month. These contractors’ records were also audited by
the ET during site inspection.
Audits of acoustic decoupling
measures for construction vessels were carried out during weekly site
inspection and the observations are summarised in Section 7.1. Audits of
SkyPier high speed ferries route diversion and speed control and construction
vessel management are presented in Section 7.2 and Section 7.3
respectively.
Detailed analysis of CWD
monitoring results collected by small vessel line-transect survey will be
provided in future quarterly reports. Detailed analysis of CWD monitoring
results collected by land-based theodolite tracking survey and PAM will be
provided in future annual reports after a larger sample size of data has been
collected.
Monitoring of CWD was conducted with two complete sets of small vessel line-transect surveys and three days of land-based theodolite tracking survey effort as scheduled. The running quarterly encounter rates STG and ANI in the reporting period did not trigger the Action Level for CWD monitoring.
Site
inspections of the construction works were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. The weekly site inspection schedule of the
construction works is provided in Appendix C. Bi-weekly site inspections
were also conducted by the IEC. Besides, ad-hoc site inspections were
conducted by ET and IEC if environmental problems were identified, or
subsequent to receipt of an environmental complaint, or as part of the
investigation work. These site inspections provided a direct means to reinforce
the specified environmental protection requirements and pollution control
measures in construction sites.
During site inspections,
environmental situation, status of implementation of pollution control and
mitigation measures were observed. Environmental documents and site records,
including waste disposal record, maintenance record of environmental equipment,
and relevant environmental permit and licences, were also checked on site. Observations were recorded in the
site inspection checklist and passed to the contractor together with the
appropriate recommended mitigation measures where necessary in order to
advise contractors on environmental improvement, awareness and on-site
enhancement measures. The
observations were made with reference to the following information during the
site inspections:
·
The EIA and EM&A requirements;
·
Relevant environmental protection laws, guidelines, and practice notes;
·
The EP conditions and other submissions under the EP;
·
Monitoring results of EM&A programme;
·
Works progress and programme;
·
Proposal of individual works;
·
Contract specifications on environmental protection; and
·
Previous site inspection results.
Good site practices were observed
in site inspections during the reporting period. Advice were given when
necessary to ensure the construction workforce were familiar with relevant
procedures, and to maintain good environmental performance on site. Regular
toolbox talks on environmental issues were organised for the construction
workforce by the contractors to ensure understanding and proper implementation of
environmental protection and pollution control mitigation measures.
During the reporting period,
implementation of recommended landscape and visual mitigation measures (CM1 –
CM10) where applicable was monitored weekly in accordance with the Manual and
no non-conformity was recorded. In case of non-conformity, specific
recommendations will be made, and actions will be proposed according to the
Event and Action Plan. The monitoring status is summarised in Appendix A.
A
summary of implementation status of the environmental mitigation measures for
the construction phase of the Project during the reporting period is provided
in Appendix A.
The Marine Travel Routes
and Management Plan for High Speed Ferries of SkyPier (the SkyPier Plan) was
submitted to the Advisory Council on the Environment for comment and
subsequently submitted to and approved by EPD in November 2015 under EP
Condition 2.10. The approved SkyPier Plan is available on the dedicated website
of the Project. In the SkyPier Plan, AAHK has committed to implement the
mitigation measure of requiring HSFs of SkyPier travelling between HKIA and
Zhuhai / Macau to start diverting the route with associated speed control
across the area, i.e. Speed Control Zone (SCZ), with high CWD abundance. The
route diversion and speed restriction at the SCZ have been implemented since 28
December 2015.
Key audit findings for the
SkyPier HSFs travelling to/from Zhuhai and Macau against the requirements of
the SkyPier Plan during the reporting period are summarised in Table 7.1. The daily
movements of all SkyPier HSFs in this reporting period (i.e., 79 to 82 daily
movements were within the maximum daily cap of 125 daily movements. Status of
compliance with the annual daily average of 99 movements will be further
reviewed in the annual EM&A Report.
In total, 510 ferry movements
between HKIA SkyPier and Zhuhai / Macau were recorded in November 2019 and the
data are presented in Appendix F. The time spent by the
SkyPier HSFs travelling through the SCZ in November 2019 were presented in Figure 7.1.
It will take 9.6 minutes to travel through the SCZ when the SkyPier HSFs adopt
the maximum allowable speed of 15 knots within the SCZ. Figure 7.1 shows that all of the SkyPier HSFs spent
more than 9.6 minutes to travel through the SCZ.
Figure 7.1: Duration of the SkyPier HSFs
travelling through the SCZ for November 2019
Note: Data
above the red line indicated that the time spent by the SkyPier HSFs travelling
through the SCZ is more than 9.6 minutes, which is in compliance with the
SkyPier Plan.
A meeting was held with the ferry
operators on 20, 27 and 28 November 2019 to review and discuss the deviation
cases happened during the past few months as well as to share experience and
recommendations to further strengthen the implementation of SkyPier Plan.
Table 7.1: Summary of Key Audit Findings against the
SkyPier Plan
Requirements in the SkyPier Plan |
1 to 30 November 2019 |
Total number of ferry movements recorded and audited |
510 |
Use diverted route and enter / leave SCZ through Gate Access Points |
0 deviation |
Speed control in speed control zone |
The average speeds of all HSFs travelling through the SCZ ranged from 10.5 to 14.0knots. All HSFs had travelled through the SCZ with average speeds under 15 knots in compliance with the SkyPier Plan. The time used by HSFs to travel through SCZ is presented in Figure 7.1. |
Daily Cap (including all SkyPier HSFs)
|
79 -82 daily movements (within the maximum daily cap - 125 daily movements). |
ET carried out the following
actions during the reporting period:
During the reporting period, ET
was notified that no dolphin sightings were recorded within the DEZ by the
contractors. The ET checked the relevant records by the
contractors and conducted competence checking to audit the implementation of
DEZ.
The current status of submissions
under the EP up to the reporting period is presented in Table 7.2.
Table 7.2: Status
of Submissions under Environmental Permit
EP Condition |
Submission |
Status |
2.1 |
Complaint Management Plan |
Accepted / approved by EPD |
2.4 |
Management Organizations |
|
2.5 |
Construction Works Schedule and Location Plans |
|
2.7 |
Marine Park Proposal |
|
2.8 |
Marine Ecology Conservation Plan |
|
2.9 |
Marine Travel Routes and Management Plan for Construction and Associated Vessels |
|
2.10 |
Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier |
|
2.11 |
Marine Mammal Watching Plan |
|
2.12 |
Coral Translocation Plan |
|
2.13 |
Fisheries Management Plan |
|
2.14 |
Egretry Survey Plan |
|
2.15 |
Silt Curtain Deployment Plan |
|
2.16 |
Spill Response Plan |
|
2.17 |
Detailed Plan on Deep Cement Mixing |
|
2.18 |
Landscape & Visual Plan |
Submitted to EPD |
2.19 |
Waste Management Plan |
Accepted / approved by EPD |
2.20 |
Supplementary Contamination Assessment Plan |
|
3.1 |
Updated EM&A Manual |
|
3.4 |
Baseline Monitoring Reports |
During the reporting period,
environmental related licenses and permits required for the construction
activities were checked. No non-compliance with environmental statutory requirements
was recorded. The environmental licenses and permits which are valid in the
reporting period are presented in Appendix D.
No construction activities-related complaint was
received during the reporting period.
Neither notification of summons
nor prosecution was received during the reporting period.
Cumulative statistics on complaints, notifications of summons and status of prosecutions are summarised in Appendix E.
Key activities anticipated in the next reporting period for
the Project will include the following:
Contract
P560 (R) Aviation Fuel Pipeline Diversion Works
● Stockpiling
of compressed materials
DCM Works:
Contract 3205 DCM works
●
DCM works
Reclamation Works:
Contract 3206 Main Reclamation
Works
● Land base ground improvement
works;
● Seawall construction; and
● Marine filling.
Airfield Works:
Contract 3301 North Runway Crossover Taxiway
● Cable
ducting works;
● Subgrade
compaction and paving works;
● Drainage
construction works;
● Operation
of aggregate mixing facility; and
● Precast
of duct bank and fabrication of steel works.
Contract 3302 Eastern Vehicular Tunnel Advance Works
● Cable
laying and ducting works;
● Trench
excavation works;
● Backfilling
and reinstatement works; and
● Site
establishment.
Contract 3303 Third Runway and Associated Works
● Plant
and equipment mobilisation
● Footing
and utilities work; and
● Site
establishment.
Third Runway Concourse and
Integrated Airport Centres Works:
Contract 3402 New Integrated Airport Centres Enabling Works
● Lateral
supports and excavation works;
● Drawpit
and duct laying works;
● Manhole
and pipe construction works; and
● Site
establishment.
Terminal 2 Expansion Works:
Contract 3501 Antenna Farm and Sewage Pumping Station
● Drainage
works;
● Boring
works; and
● Pipe
installation.
Contract 3502 Terminal 2 Automated People Mover (APM) Depot
Modification Works
● Site
clearance.
Contract 3503 Terminal 2 Foundation and Substructure Works
● Site establishment;
● Utilities, drainage, and road
work; and
● Piling and structure works.
Automated People Mover (APM)
Works:
Contract 3602 Existing APM System Modification Works
● Site
establishment; and
● Modification
works at APM depot.
Airport Support Infrastructure & Logistic Works:
Contract 3721 Construction Support Infrastructure Works
● Excavation
for utilities works; and
● Construction
of utilities
Contract 3801 APM and BHS Tunnels on Existing Airport
Island
● Site
establishment;
● Cofferdam
installation for box culvert;
● Rising
main installation;
● Drilling
and grouting works;
● Piling
and foundation works
● Demolition
works; and
● Site
clearance.
The key environmental issues for
the Project in the coming reporting period expected to be associated with the
construction activities include:
● Generation of dust from
construction works and stockpiles;
● Noise from operating equipment
and machinery on-site;
● Generation of site surface
runoffs and wastewater from activities on-site;
● Water quality from DCM works and
marine filling;
● DEZ monitoring for ground
improvement works (DCM works) and seawall construction;
● Implementation of MMWP for silt
curtain deployment;
● Sorting, recycling, storage and
disposal of general refuse and construction waste;
● Management of chemicals and
avoidance of oil spillage on-site; and
● Acoustic decoupling measures for
equipment on marine vessels.
The implementation of required
mitigation measures by the contractors will be monitored by the ET.
A
tentative schedule of the planned environmental monitoring work in the next
reporting period is provided in Appendix B.
With reference to Appendix E of the Manual, it is noted that the key assumptions adopted in approved EIA report for the construction phase are still valid and no major changes are involved. The environmental mitigation measures recommended in the approved EIA Report remain applicable and shall be implemented in undertaking construction works for the Project.
The key
activities of the Project carried out in the reporting period included
reclamation works and land-side works. Reclamation works included DCM works,
marine filling and seawall construction. Land-side works involved mainly
airfield works, foundation and substructure work for Terminal 2 expansion,
modification and tunnel work for APM and BHS systems, and preparation work for
utilities, with activities include site establishment, site office
construction, road and drainage works, cable ducting, demolition of existing
facilities, piling, and excavation works.
All the monitoring works for
construction dust, construction noise, water quality, construction waste,
landscape & visual, and CWD were conducted during the reporting period in
accordance with the Manual.
Monitoring
results of construction dust, construction noise, construction waste, and
CWD did not trigger the corresponding Action and Limit Levels during the
reporting period.
The water quality monitoring
results for DO, turbidity, total alkalinity, nickel, and chromium obtained
during the reporting period were within the corresponding Action and Limit
Levels stipulated in the EM&A programme. Relevant investigation and follow-up
actions will be conducted according to the EM&A programme if the
corresponding Action and Limit Levels are triggered. For SS, one testing result
triggered the relevant Action Level, and the corresponding investigation was
conducted accordingly. The investigation findings concluded that the case was
not related to the Project. To conclude, the construction activities in the
reporting period did not introduce adverse impact to all water quality
sensitive receivers.
Weekly site inspections of the
construction works were carried out by the ET to audit the implementation of
proper environmental pollution control and mitigation measures for the Project.
Bi-weekly site inspections were also conducted by the IEC. Site inspection
findings were recorded in the site inspection checklists and provided to the
contractors to follow up.
On the implementation of the
SkyPier Plan, the daily movements of all SkyPier HSFs in November 2019 were in
the range of 79 to 82 daily movements, which are within the maximum daily cap
of 125 daily movements. A total of 510 HSF movements under the SkyPier Plan
were recorded in the reporting period. The average speeds of all HSFs
travelling through the SCZ ranged from 10.5 to 14.0 knots. All HSFs had
travelled through the SCZ with average speeds under 15 knots in compliance with
the SkyPier Plan. Zero deviation from the diverted route in November 2019 were
recorded in the HSF monitoring. In summary, the ET and IEC have audited the HSF
movements against the SkyPier Plan and conducted follow up investigations or
actions accordingly.
On the implementation of
MTRMP-CAV, the MSS automatically recorded the deviation case such as speeding,
entering no entry zone and not travelling through the designated gates. ET
conducted checking to ensure the MSS records all deviation cases accurately.
Training has been provided for the concerned skippers to facilitate them in
familiarising with the requirements of the MTRMP-CAV. Deviations including
speeding in the works area, entered no entry zone, and entry from
non-designated gates were reviewed by ET. All the concerned captains were
reminded by the contractor’s MTCC representative to comply with the
requirements of the MTRMP-CAV. The ET reminded contractors that all vessels
shall avoid entering the no-entry zone, in particular the Brothers Marine Park and the Sha
Chau & Lung Kwu Chau Marine Park. Three-month rolling programmes for
construction vessel activities, which ensures the proposed vessels are
necessary and minimal through good planning, were also received from
contractors.
[1]
The Manual is available on the Project’s dedicated website (accessible at: http://env.threerunwaysystem.com/en/index.html).